How is PERT estimation applied in agile environments

0 votes
I’m trying to apply PERT in an Agile setup—does that even work well with iterative sprints, or is it more suited for Waterfall?
5 days ago in PMP by Parshvi
• 6,340 points
29 views

2 answers to this question.

0 votes

PERT (Program Evaluation and Review Technique) is a method for predicting the time required to finish a task, especially when there is ambiguity about how long it will take. In Agile, PERT can be used to estimate work efforts for stories, epics, and sprints. This is how PERT estimating works in Agile.

  • PERT uses three-time estimates: optimistic (O), pessimistic (P), and most likely (M). The calculations for these estimates are as follows: Expected time=6O+4M+P
  • Apply to Agile User Stories: In Agile, utilize PERT to estimate effort on user stories or epics. This helps to account for uncertainties in a task's complexity, particularly when predicting how long something will take owing to unexpected challenges.
  • Track and Adjust Estimates: As the project advances, compare actual performance to PERT estimates. Use this information to adjust future time predictions, resulting in a more precise projection for the next sprints.

PERT is an effective method for estimating activities with more uncertainty in Agile environments, and it can be especially beneficial during planning poker or backlog refinement meetings.

answered 5 days ago by Naira
0 votes

PERT (Program Evaluation and Review Technique) is a method for predicting the time required to finish a task, especially when there is ambiguity about how long it will take. In Agile, PERT can be used to estimate work efforts for stories, epics, and sprints. This is how PERT estimating works in Agile.

  • PERT uses three-time estimates: optimistic (O), pessimistic (P), and most likely (M). The calculations for these estimates are as follows: Expected time= O+4M+P​/6
  • Apply to Agile User Stories: In Agile, utilize PERT to estimate effort on user stories or epics. This helps to account for uncertainties in a task's complexity, particularly when predicting how long something will take owing to unexpected challenges.
  • Track and Adjust Estimates: As the project advances, compare actual performance to PERT estimates. Use this information to adjust future time predictions, resulting in a more precise projection for the next sprints.

PERT is an effective method for estimating activities with more uncertainty in Agile environments, and it can be especially beneficial during planning poker or backlog refinement meetings.

answered 5 days ago by Naira

Related Questions In PMP

+1 vote
1 answer
0 votes
1 answer

What does a project manager do?

As a Project Manager of an organization, ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points

edited Jul 22, 2020 by Sirajul 821 views
0 votes
1 answer

Which is the best project manager certification?

Although there are many certifications available that ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
920 views
0 votes
1 answer

What is the best path to become a Project Manger?

Assuming you don't have sufficient experience, Here are ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
1,031 views
0 votes
1 answer

What's the salary of a project manager?

Project managers enjoy the most lavish salaries ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
970 views
0 votes
1 answer

How is activity sequencing different in Agile vs Waterfall?

Activity sequencing is an important aspect of ...READ MORE

answered 4 days ago in PMP by Naira
20 views
0 votes
1 answer

How do you measure success in an Agile project?

Agile success isn’t just about on-time delivery—it’s ...READ MORE

answered Mar 25 in PMP by Naira
67 views
webinar REGISTER FOR FREE WEBINAR X
REGISTER NOW
webinar_success Thank you for registering Join Edureka Meetup community for 100+ Free Webinars each month JOIN MEETUP GROUP