Velocity is useful in estimating future sprint capability, but it is not a failsafe. Key challenges include:

  • Team Performance Fluctuations - Velocity varies depending on team experience, task complexity, and external disturbances.

  • Scope Creep and Changing Priorities - If velocity projections need to change throughout a sprint, they become incorrect.

  • New Teams Face Difficulties - Establishing a consistent velocity baseline is hard due to a lack of historical data.

  • External Dependencies - If work is dependent on outside teams or vendors, their delays affect overall velocity.

  • Ignoring Non-Development Work - Administrative tasks, meetings, and unexpected roadblocks can diminish actual work time.

To improve accuracy, real historical data can be used to refine velocity computations and update forecasts on a regular basis based on observed patterns.

answered Apr 4 by Naira

Related Questions In PMP

0 votes
1 answer

What are the security concerns in using cloud-based PM tools for confidential projects?

Cloud-based PM solutions offer convenience but pose ...READ MORE

answered Apr 4 in PMP by Naira
55 views
0 votes
1 answer

What are the biggest challenges in adopting Agile methodologies?

The biggest challenges in adopting Agile methodologies ...READ MORE

answered Nov 5, 2024 in PMP by Ali
167 views
0 votes
1 answer
0 votes
1 answer

Which is the best project manager certification?

Although there are many certifications available that ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
915 views
0 votes
1 answer

What is the best path to become a Project Manger?

Assuming you don't have sufficient experience, Here are ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
1,024 views
+1 vote
1 answer

How do I become a Project manager with no experience?

Since you don't have any prior experience ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
996 views
0 votes
3 answers

Which is the best project management software?

Today, with the evolving technology, every project ...READ MORE

answered Jul 27, 2020 in PMP by GurwinderKaur
• 380 points
893 views
0 votes
1 answer
0 votes
1 answer

What are the benefits of WIP limits (Work In Progress limits) in Kanban?

WIP limits help teams stay focused and ...READ MORE

answered Apr 4 in PMP by Naira
40 views
webinar REGISTER FOR FREE WEBINAR X
REGISTER NOW
webinar_success Thank you for registering Join Edureka Meetup community for 100+ Free Webinars each month JOIN MEETUP GROUP