Portfolio Risk Management How to develop it

0 votes

Hello everyone! I'm defining a Portfolio Risk Management but I'm new at the topic and I have some doubts. Anyone has done it before and can help me?


My question: Example of metrics for overall portfolio risks (without making risk management on each project?
 

Aug 13, 2020 in PMP by anonymous
• 65,770 points
528 views

1 answer to this question.

0 votes


You can derive many metrics for your portfolio depending on your need. For example:

(1) Number of risky projects - a simple measure
(2) Number of cross-project risks - those risks that are capable of causing risks in other projects
(3) Depth of related risks tree - if you have (2), then you can estimate how deep a risk trigger could go

etc.

I understand that some project risks could also be portfolio-level risks. But, the PM has to ensure the success of each project. Therefore, I don't think that there is a way out of risk assessment for each project within the portfolio.

answered Aug 13, 2020 by Raina Neman

Related Questions In PMP

0 votes
1 answer

Portfolio Risk Management: How to develop it?

A portfolio is not about projects at ...READ MORE

answered Aug 5, 2020 in PMP by David Samon
618 views
0 votes
1 answer

What are all Various Risk Status in Project?

To be honest, Ganesh, I probably would not think ...READ MORE

answered Aug 13, 2020 in PMP by Richa sharma
9,649 views
0 votes
1 answer
0 votes
1 answer

How to simplify project management?

It really depends on whether there is ...READ MORE

answered Aug 13, 2020 in PMP by Roshni
• 10,480 points
528 views
0 votes
1 answer

Project Management Sessions to create awareness

Create an attractive presentation (based on the ...READ MORE

answered Aug 13, 2020 in PMP by Reshma
668 views
webinar REGISTER FOR FREE WEBINAR X
REGISTER NOW
webinar_success Thank you for registering Join Edureka Meetup community for 100+ Free Webinars each month JOIN MEETUP GROUP