How do you estimate time and resources in Agile projects

0 votes
How can Agile teams effectively estimate time and resources to ensure successful project delivery without compromising flexibility and adaptability?
Nov 10, 2024 in PMP by Hoor
• 4,230 points
78 views

1 answer to this question.

0 votes

Estimating Time and Resources in Agile Projects:

  1. Story Points & Velocity: Teams use story points to estimate effort, not time. Velocity measures how many points the team completes per sprint, helping estimate future work.
  2. Planning Poker: Team members assign story points to tasks and then discuss them to reach a consensus on effort and complexity.
  3. Time-Boxing: Work is planned within fixed sprint durations (2-4 weeks), focusing on what can be completed, not exact hours.
  4. Resource Allocation: Estimate team capacity and assign resources based on skill and availability, adjusting as the project evolves.

Example:

In a feature development project, the team estimates tasks in story points (e.g., 8 for design, 5 for dev). With a velocity of 20 points per sprint, they estimate two sprints to finish the feature.

answered Nov 10, 2024 by Alia

Related Questions In PMP

0 votes
1 answer

How do you deal with scope creep in Agile projects?

From my experience, Agile scope creep management ...READ MORE

answered Nov 18, 2024 in PMP by Sufi
78 views
0 votes
1 answer

How do you manage research and development projects in pharma?

Managing Research & Development projects in pharma ...READ MORE

answered Jan 2 in PMP by Sufi
41 views
0 votes
1 answer

Which is the best project manager certification?

Although there are many certifications available that ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
815 views
0 votes
1 answer

What is the best path to become a Project Manger?

Assuming you don't have sufficient experience, Here are ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
875 views
+1 vote
1 answer

How do I become a Project manager with no experience?

Since you don't have any prior experience ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
888 views
0 votes
3 answers

Which is the best project management software?

Today, with the evolving technology, every project ...READ MORE

answered Jul 27, 2020 in PMP by GurwinderKaur
• 380 points
799 views
0 votes
1 answer

What are the most common Agile metrics and how do you track them?

The most common Agile metrics and how ...READ MORE

answered Nov 7, 2024 in PMP by Anu
122 views
0 votes
1 answer

How do you implement Agile in a hybrid work environment?

Agile in a hybrid working environment does ...READ MORE

answered Nov 10, 2024 in PMP by Sonia
143 views
webinar REGISTER FOR FREE WEBINAR X
REGISTER NOW
webinar_success Thank you for registering Join Edureka Meetup community for 100+ Free Webinars each month JOIN MEETUP GROUP